Advanced Power Studies Contact Us
APS Test & Commissioning

Site Acceptance Testing & Protection Commissioning with End-to-End Scheme Verification

APS provides specialist SAT, protection commissioning and end-to-end scheme verification for MV, HV and EHV substations and grid connection points, confirming that protection, control, communication interfaces and associated primary plant operate correctly as an integrated system before energisation.

MV / HV / EHVProtection commissioning and end-to-end scheme verification.
SAT & End-to-End Protection Commissioning Services
GPS-Synchronised Injection · IEC 61850 · Scheme Verification
Service Scope

Site Acceptance Testing & End-to-End Protection Commissioning

Specialist SAT, protection commissioning and GPS-synchronised end-to-end scheme verification for MV, HV and EHV substations and grid connection points — providing the traceable technical evidence required for safe energisation, client acceptance and network operator approval.

Overview

Protection systems are rarely misapplied because of a relay hardware failure alone. In practice, protection misoperations are most often caused by incorrect settings, interface mismatches, wiring errors, CT or VT polarity problems, communication faults, trip-circuit defects, incomplete interlocking or changes that survive individual device testing but only become visible when the complete scheme is tested as a system under installed site conditions.

Factory Acceptance Testing confirms that equipment and panels meet the specified requirements before delivery. Site Acceptance Testing confirms that the installed equipment, wiring, interfaces and functional logic perform correctly on site. Protection commissioning then verifies that the complete protection and control scheme is ready for safe service. These three stages are distinct and complementary — passing a FAT does not substitute for a proper SAT and protection commissioning programme.

APS focuses on this critical system-level stage. The service verifies that protection settings, current and voltage signals, tripping paths, interlocking logic, communication links, alarms, indications and breaker responses all operate correctly as an integrated system before the substation or grid connection is energised. For line protection schemes, GPS-synchronised end-to-end testing allows realistic fault conditions to be applied simultaneously at both terminals, confirming that both ends of the protected circuit operate coherently before the circuit is placed into service.

Test results are interpreted against design schematics, protection settings, approved drawings, functional descriptions and acceptance limits. The objective is a clear technical position supported by traceable test evidence — not simply a collection of recorded values — giving clients, contractors and network operators documented confidence that the protection system will operate correctly, selectively, dependably and securely from the first day of energisation.

FAT, SAT & Commissioning — The Three Stages

Factory Acceptance Testing, Site Acceptance Testing and protection commissioning are three distinct and complementary stages. Each confirms different things and none substitutes for another. A clear understanding of what each stage does — and does not — verify is important for planning an effective commissioning and acceptance programme.

Factory Acceptance Testing (FAT) confirms that individual equipment items and panels meet the specified functional requirements in a controlled factory environment. Relay settings can be loaded and tested, panel wiring can be checked, and communications interfaces can be verified against the engineering specification. FAT evidence provides confidence that the equipment is correctly built and configured before it leaves the factory. It does not confirm that the equipment will behave correctly once installed, wired to the site CT and VT secondaries, connected to the substation auxiliary supplies, interfaced with other equipment on site, or integrated into the protection scheme as a system.

Site Acceptance Testing (SAT) confirms that the installed equipment, wiring, interfaces and functional logic perform correctly under site conditions. SAT covers checks that can only be completed on site — verification against as-installed wiring, confirmation of correct auxiliary supply connections, insulation testing of installed circuits, and functional checks through the installed current and voltage transformer circuits. SAT is particularly important where equipment has been transported, handled on site, installed in a substation environment, or modified after factory testing.

Protection Commissioning verifies the complete protection and control scheme — not individual relays or panels in isolation, but the whole system including CT and VT secondary signals, settings, trip circuits, interlocks, communication channels, alarms, indications and breaker responses. It provides the final confirmation, before energisation, that the scheme will operate correctly, selectively, dependably and securely in service.

APS can support any or all three stages, acting as principal tester, independent witness or technical reviewer depending on the project structure. For projects where a contractor carries out FAT and SAT activities, APS can provide independent oversight, hold-point witnessing and technical sign-off before energisation is approved.

Key Services

The test scope is adapted to the project requirements and may cover the full protection and control scheme or specific aspects where independent verification is required. Services span pre-energisation acceptance, protection commissioning, end-to-end scheme testing and functional interface verification.

  • Site acceptance testing of installed primary plant, protection and control equipment More info
  • Pre-energisation commissioning checks, wiring verification and review of as-installed condition against approved design information More info
  • Secondary injection testing and relay settings verification against the approved protection setting schedule More info
  • Protection element pickup, timing, characteristics and logic verification — overcurrent, earth fault, differential, distance, voltage, frequency and other applicable functions More info
  • Primary injection testing to confirm CT and VT signals, ratio, polarity and the complete current path to protection relays More info
  • Trip-circuit, trip-relay and circuit-breaker trip-path functional verification, including selectivity, grading and blocking logic confirmation More info
  • GPS-synchronised end-to-end testing of line protection schemes across both substation terminals More info
  • Line differential, distance, permissive, blocking, intertripping and unit protection scheme verification under simulated internal and external fault conditions More info
  • Teleprotection and communications-aided scheme verification — channel timing, signalling, permissive and blocking logic checks More info
  • Control, indication, interlock, alarm, auto-reclose and trip sequence functional testing More info
  • Local, remote and control-room command verification; SCADA point-to-point signal checks More info
  • IEC 61850 scheme checks, including GOOSE messaging, virtual wiring verification and controlled use of test and simulation modes More info

End-to-End Testing & GPS-Synchronised Injection

End-to-end testing verifies that a line protection scheme operates correctly as a complete system by testing both ends of the protected circuit simultaneously. The method is the definitive pre-energisation check for line protection schemes because it is the only approach that confirms the coordinated behaviour of protection equipment at both terminals under realistic fault conditions — before the circuit is placed into service.

For schemes where correct operation depends on signalling or communication between the two ends — line differential protection, distance protection with permissive or blocking teleprotection, intertripping schemes and unit protection — individual relay testing at each end cannot confirm that the scheme will operate correctly as a whole. End-to-end testing does, because it exercises the complete signal path: CT and VT secondaries, relay inputs, relay logic, communication channels, teleprotection signalling, relay outputs, trip circuits and circuit-breaker trip responses at both terminals.

GPS-synchronised injection uses precision GPS timing to apply test voltages and currents simultaneously at both terminals from independent test sets. Because the injection at each end is phase-aligned and time-stamped with GPS accuracy, it is possible to reproduce realistic internal and external fault scenarios — including through-fault stability tests, zone boundary cases and evolving fault conditions — that would otherwise be impossible to verify without the circuit being live.

The test programme typically covers: operation under simulated faults within the protected zone, stability under through faults outside the zone, correct discrimination between zones for distance protection, channel timing and signalling for teleprotection schemes, and coherent operation of auto-reclose sequences where applicable. Results are recorded with GPS timestamps and relay event data, providing a complete and traceable end-to-end test record that supports energisation approval and acceptance sign-off.

For IEC 61850 schemes using GOOSE-based protection, end-to-end testing also verifies virtual wiring, multicast GOOSE logic and communication performance across the substation LAN and inter-substation WAN where applicable.

Standards & Applicable Codes

Testing is carried out in line with recognised standards, good engineering practice and project-specific requirements.

  • IEC 60255 series — Measuring relays and protection equipment: common requirements, functional requirements and testing
  • IEC 61869 series — Instrument transformers: general requirements, current transformers, voltage transformers and commissioning tests
  • IEC 61850 series — Communication networks and systems for power utility automation, including GOOSE messaging and digital substation engineering
  • IEC 62271 series — High-voltage switchgear and controlgear: circuit-breakers, disconnectors, AC metal-enclosed switchgear and GIS
  • IEEE Power System Relaying Committee (PSRC) guidance — protection system commissioning, end-to-end testing practices and teleprotection channel testing
  • Manufacturer relay configuration guides, approved protection setting schedules and factory test evidence
  • Grid code requirements applicable to the connection point and asset type
  • DNO / TSO project-specific acceptance criteria and commissioning procedures
  • Client and EPC project specifications, approved drawings, functional descriptions and inspection and test plans

Typical Applications

The service is suitable for any project requiring independent, structured commissioning and acceptance evidence for protection and control schemes, from individual feeder protection to complex multi-terminal and busbar schemes at transmission voltage.

  • New substation and grid connection commissioning
  • Renewable generation projects — solar PV, wind and hybrid plants
  • Battery energy storage systems and grid-scale BESS connections
  • Data centres and mission-critical HV connections
  • Industrial plants, process facilities and private HV networks
  • MV, HV and EHV protection and control schemes
  • Substation extension, replacement and refurbishment works
  • Protection and control upgrade or retrofit projects
  • Circuit, transformer, busbar, feeder and line protection commissioning
  • Line protection end-to-end testing between substations
  • Post-fault investigation, root-cause analysis and re-commissioning
  • Independent witnessing of contractor SAT and commissioning activities
  • Network operator, client and lender technical acceptance support

Deliverables

The scope of documentation is agreed with the client at the outset and adapted to meet project, network operator or asset-management requirements.

  • Method statements and inspection and test plans (ITPs)
  • Protection commissioning test sheets with measured results and pass/fail assessment against the approved setting schedule
  • SAT records for primary plant, protection and control equipment
  • End-to-end test reports with GPS event timestamps, relay records and scheme operation evidence
  • Trip-circuit verification records and circuit-breaker test results
  • Non-conformance identification and corrective-action recommendations
  • Marked-up drawings and as-tested records
  • Consolidated technical evidence package for energisation approval and DNO/TSO sign-off

Technical Value

A protection scheme is only as reliable as its weakest interface. Testing an individual relay does not prove that the full protection system will operate correctly in service. The complete scheme depends on correct CT and VT inputs, correct settings, correct logic, healthy trip circuits, functional interlocks, reliable communication channels, correct breaker response and accurate indication to operators. Any one of these elements can fail without triggering an alarm during normal operation, and each is a potential source of a delayed, incorrect or absent trip under fault conditions.

By testing the system as an integrated whole, APS helps identify latent defects that may not be found during standalone equipment testing. These may include swapped CT polarity, incorrect VT phasing, crossed trip wiring, wrong relay logic, incomplete interlocking, incorrect teleprotection signalling, disabled protection functions, incorrect SCADA indication or a communications delay that reduces scheme dependability or security. These defects are typically straightforward to correct when found during commissioning and can be very difficult to manage once the circuit is in service.

End-to-end testing is particularly important for line protection schemes because correct operation depends on the coordinated behaviour of equipment at both ends of the protected circuit. GPS-synchronised injection allows realistic fault scenarios to be applied simultaneously at both terminals, enabling the operation, stability, discrimination and selectivity of the complete scheme to be verified before the circuit is energised. This is the only reliable method of confirming that the scheme will operate correctly for faults within the protected zone and remain stable for faults outside it.

APS provides the traceable technical evidence required for safe energisation, client acceptance and network operator approval — giving all parties documented confidence that the protection and control system will operate correctly, selectively, dependably and securely from the first day of energisation.